A strategy to turn marginal gold- miner East Rand Proprietary Mines(ERPM) into a 400 kg/m producer has hit a snag, but managconcrete crushing plant for sale, concrete jaw crusher, cone crusher supplierement is
hopeful that the project will get back on track next month. Towards
the end of last year, the century-old miner announced plans to mine
Boksburg’s landmark Cason dump, with the intention of adding
78 kg of gold production to ERPM’s usual output of 135 000
oz/y.
However, operations director Grant Dempsey told Mining Weekly last
week that the R46,5-million project was delayed due to problems
with finalising a deposition site, initially intended to be a
slimes dam in Benoni.
But, said Dempsey, the company has not been able to conclude
arrangements with the management of this site.
“We are currently looking at altern-atives and we hope to
proceed with the project in April,” he commented.
The company last year planned for the operation to be in full swing
by now, and envisaged mining 100 000 t by January and 200 000 t
– full tonnage – by February. At the time, Dempsey
pointed out that the tightness of the schedule for the start-up of
mining was to add additional gold ounces to the mine’s
output, and warned that ERPM’s entire production plan would
have to be rethought if the deadlines were not met.
It is anticipated that, once the project gets under way, it could
create about 150 new jobs, and have a life of about eight years.
Gold would be recovered at a cost of R73 000/kg, using a
straightforward carbon-in-leach process.
The R46,5-million capital expend-iture was allocated mainly for
infra-structure upgrading, including the recommissioning of disused
parts of ERPM’s processing plant at its Central shaft,
located in Elsburg – between Boksburg and Germiston.
Dempsey explained that subcon-tractors have already completed most
of the work and one team is currently still on site, carrying out
remedial work. He said that, despite the delay, the project would
get off the ground.
“This is not a crisis; it’s a delay. We hope to begin
mining in April,” he said, adding that the hold-up would not
significantly affect ERPM’s pro-duction.
This is not the first time that the mine has planned to recover
gold from Cason dump. A similar initiative was attempted by
ERPM’s previous owner, before the mine went into liquidation
in 1999, but faced staunch opposition from local communities.
This time, noise- and dust-sup-pression measures have been put in
place, and the dump is to be mined from the south side, ensuring
that the dump itself shields the operation from wind. After
completion of the reclamation operation, a rehabilitation project
will be initiated.