Australian mining firm Red Back Mining announced in May this year aresource inventory upgrade for the Chirano gold project in Ghana
comprising indicated and inferred resources of 26,77-million tons
grading 2,2 g/t for 1 873 000 oz.
Consultant Resource Service Group (RSG) completed its analysis of
the pit optimisation studies and has estimated that, at a gold
price of $300/oz, Chirano is optimised at a production rate of
two-million tons a year grading 2,3 g/t to produce about 140 000
oz/y of gold over a mine life of seven and a half years. Scoping
study economics indicate operating costs of about $200/oz, which
represents $14,50/t of ore milled.
Red Back entered into a strategic relationship with fellow
African-focusused mobile crusher for saleed gold group Resolute Mining in April this
year.
The alliance came after an announcement that a $5,1-million
capital-raising action would be undertaken to fund a bankable
feasibility study (BFS) on the Chirano gold project.
Red Back MD Ross Ashton said the raising would secure funding for
the BFS, signalling a key step forward for the project, which was
given the green light by the Ghanaian Ministry of Mines in January
this year to proceed with an environmental-impact statement.
"The decision by the Ministry of Mines, recently separated from the
Ministry of Lands, Forestry and Mines, should be seen as a strong
commitment by the new government to promote mining and mineral
exploration in Ghana," says Ashton.
The news of the ministry decision came together with an
announcement by Red Back to up the pay on its exploration plans for
Chirano in 2002 after it had received encouraging drilling results
which identified three new openpit deposits and pointed to
significant extensions between known pits, including a potential
2,5 km super-pit.
Ashton says that drilling between the existing Tano (a 190 000 oz
resource) and the Paboase (a 358 000 oz resource) deposits and in
the 200 m gap between the Obra (a 594 000 oz resource) and the Tano
deposits had returned encouraging results.
"This opens the possibility that the Obra, Tano and Paboase pits
may be extended or even linked into a 2,5-km-long super-pit," he
explains.
The BFS for the Chirano gold project, estimated to cost $3,6
million, has been awarded to Lycopodium and will examine the
suitability of relocating the Obotan plant to Chirano and adapting
the plant design to Chirano ore.
Lycopodium, which designed and constructed the Obotan plant for
Resolute in 1996 and the nearby Bibiani plant for Ashanti
Goldfields, has been awarded the contract to complete the
engineering and processing design for Chirano and to coordinate the
BFS in conjunction with Red Back technical staff.
The BFS is scheduled to be completed in October this year, which
approximately coincides with the completion of the
environmental-impact statement (EIS). The EIS scoping report and
terms of reference were lodged at the Ghana Environmental
Protection Agency in the first quarter of the year and collection
of additional baseline data is continuing.