Mumbai: Infrastructure major, Larsen & Toubro (L&T) received a contract to build facilities including gas processing plant from the state-run Saudi Aramco. L&T’s expertise will be delivered at the Saudi body’s Midyan gas field, wherein a plant with a processing capacity of 75 million standard cubic feet per day of non-associated gas and 4,500 barrels of condensate per day will be developed.The project is expected to be functional by mid-2016 and will enable efficient power generation. Briefing upon the project, Fahad al-Helal, Executive Director of Project Management at Aramco said, “The project will include building two pipelines of 98 km length to deliver sales gas and hydrocarbon liquids to a power plant near (the western city of) Duba.”
Though the company refrained from disclosing the actual contract value, the industry sources estimates it to be worth not less than $300 million.
EPC World News Bureau