State-owned utility Eskom made a commitment on Thursday to limitits unplanned outages to a maximum of 2 500 MW as South Africa enters ajigging machines manufacturer
new phase of power rationing.
Speaking at press conference following a meeting with key industrial users and municipalities, CEO Jacob Maroga said that the country still needed to save 3 000 MW between March and
July, but that this would have to be divided more equally than it had
during the stabilisation phase between February and March.During
that period, the South African mining industry was particularly hard
hit and was forced to cut its power usage by 10%, which negatively
affected mine output. The country’s mining production fell by 10,7% in
January, with the gold and platinum industries taking the biggest
knock. Maroga said that it, in asking the industrial,
commercial and residential customers to take the pain of the 3 000 MW
cuts, which would be implemented through a system of ‘preemptive load
shedding’, Eskom would also make a supply side commitment to reduce
unplanned events at its power stations.It is now widely accepted
that supply side instability in late January and early February was the
main cause of nationwide power cuts, and Maroga acknowledged on
Thursday that as much as 6 000 MW of its available capacity had been
down due to unplanned events. Much of this related to load losses
caused by insufficient and poor quality coal, which precipitated a
review by Eskom of its coal procurement and stockpile systems.The
utility announced last month that it aimed to procure an additional
45-million tons of coal over two years to raise its power stations’
stocks to over 20 days.The next round of rationing, which would
include residential and commercial load shedding schedules to be
published on March 24 and implemented on March 31, planned for 1 800
MW of the 3 000 MW to be saved from commercial and residential
customers with the balance arising from the key industrial customers,
including mines.Commercial and municipal customers have
been asked by Eskom to provide evidence of cutbacks if these have been
made and should a municipality be able to prove that it has made a 10%
cut, residents in those areas will be exempted from the load shedding
schedule. Maroga acknowledged that load shedding was an
undesirable and blunt instrument and said that he hoped to enter a more
sophisticated, high-conservation phase (incorporating both incentives
for saving, and disincentives for inefficiency) within the next few
months.