Step of soil nail wall constructionStep 1. Require height of each layer of soil nailing construction face according to the design file, Pre-precipitation to 0.5m below each layer of construction face.
Step 2. Start to do soil nailing construction, side walls should adopt a minicomputer or spade to cutting and clearance to ensure the smooth slope and meet the design requirements.
Step 3. Embedded in control flag that indicate the wall thickness of the concrete.
Step 4. Clear the slope virtual earth, spray first level layer of concrete.
Step 5. Should do water conservation two hours after concrete injection, time of conservation determined by the temperature, it should be 3-7 days.
Step 6. Begin setting soil nails after the final setting of concrete surface.
Step 7. Make a platform close to the soil nail wall accordance with the design degree of soil nails.
Step 8. Begin drilling with spiral drilling machine.