THengineering design and drawing consultant for vertical grinding millE Ministry of Mines and Mining Development has finally agreed to transfer iron ore claims to Essar, a move that would result in the Indian firm completing its takeover of Zisco.The move comes after intense lobbying by Cabinet on Monday to expedite the transaction, amid revelations that Essar were becoming impatient.
Welshman Ncube, Industry and Commerce minister, told Standardbusiness on Thursday that Obert Mpofu's ministry had written him a letter agreeing to transfer the iron claims, key for the completion of the deal.
"They wrote a letter to us. It has everything we wanted except three or four claims in Mwanezi, which they have not included in the letter," Ncube said, adding that he had written another letter inquiring about the omission.
"They have invited Essar to come and have discussions on the condition for the renewal of the Special Grant."
The special grant was issued in favour of Bimco, Zisco's minerals arm, but had expired. It allows exploration to take place in an area covering 41 000 hectares.
The transfer of the iron ore claims was the outstanding issue and a condition precedent in the finalisation of the deal.
The claims are held by Zisco and Bimco. These include Buchwa, Ripple Creek and Mwanezi.
Claims at Buchwa Mine, even though existent on paper, had become useless as Zisco had stopped operating at Buchwa Mine a long time ago, on the basis that the iron ore, although estimated at 30 million tonnes underground, was now too deep. It was no longer profitable to access the iron ore.
The Ripple Creek claims in Kwekwe were being used by Zisco at the time it stopped producing in 2008.
Claims in Mwanezi are in two categories: Special grant issued in favour of Bimco and 20 other claims explored by Bimco in two different areas believed to have high-grade ore.
Initially, the ministry of Mines wanted to transfer Buchwa and Ripple Creek claims, but was not prepared to renew the special grant in Mwanezi, saying anyone interested should approach the ministry.
However, the ministry of Industry argued that iron ore at Ripple Creek was of low-grade because it had 54% iron content.
During the due diligence exercise, engineers told Ncube's ministry that to successfully revive Zisco and use blast furnace number four, the iron content generally accepted, had to be between 64% and 74%.
Essar won the right for Zisco's controlling stake last year after agreeing to take over the troubled steel maker's foreign debt of over US$400 million.
The transaction would result in the creation of two companies, New Zim Steel (NZS) and New Zim Minerals (NZM), burying the ghost of Zisco.
Government would have a 40% stake in NZS with Essar owning the remainder.
In NZM, Essar would have 80% with government owning 20%.
According to Essar's plan unveiled last year, US$115 million would be injected in NZS under phase 1 with a projected output of 500 000 metric tonnes per annum within 18 months.
The production was expected to rise to 1,2 million metric tonnes per month under phase 2 after an injection of US$275 million.